Displaying issues in a Gantt chart

To display issues in a Gantt Chart, at least a start date,  due dates or milestones timeline needs to be set. 

Screenshot_2019-10-07_at_4.06.05_PM.png 

  1. The issue only will be displayed when at the minimum the timeline of the task or milestones has been set.  
  2. Task and milestone timeline has will affect how information reflects in the Gantt chart. In the scenario that:
    - if the milestone has the release date (start and due date), the bar will display the release date with all the task that grouped under the milestone regardless whether timeline of a task has been set.
    - if task timeline has been set but not the milestone release date, task info will reflect in the Gantt chart view with the milestone. 
    - if neither the milestone nor the task has the timeline set, both information will not reflect in the Gantt chart. 